January

We were able to resume our seemingly endless task of laying concrete to the base of the canal. 

Read More

February

Great progress was made with the continuing construction of the roadway along the top of the left hand canal bank which is nearing completion Summerhill.

Read More

March

We laid more concrete and continued shaping the batter to the marina side of the canal.

+ Green & Grounds WInter report
+ Fosseway Volunteer Day

Read More

April

A big cheer to Barry Parkes and Rick Walters for the completion of the Historic Bywash at lock 24, well almost. 

Read More

May

Removal of the Big Pipe got underway with the guys  moving about 20 sections per hour using a Telehandler on loan from Finning at Cannock.

Read More

June

Work on the Concrete Canvas on the left hand bank has paused whilst we sort out a few minor technical problems with the grouting. 

 

Read More

July

And that finishes the base.  There is still a lot of concreting to do in reinforcing the canal  bank batter.  But although time consuming this is not such a slog that the canal base proved to be.

Read More

August

The top story of this blog has got to be the working of the clay in the winding hole.  A 13 tonne JCB digger had been offered to us on free loan for a long weekend.

Read More

September

At last we have completed the concrete reinforcing half way up the left hand canal bank batter, which is lined with Concrete Canvas.

Read More

October

More big pipe sections were cut down to size, the cut off portion being taken to Darnford Park.

+ Darnford Park Training Day
+ Summerhill Progress Report
 

Read More

November

The big news of this blog is that the missing sections of the penstock  have been replaced.  

+ Green Team and Corporate volunteers at Summerhill 

Read More

December

The A51 approach has become a 'no go' area, a sea of mud.  However, to keep the job going we have had to do some serious 'mud wallowing'.

Green & Grounds Team Autumn Report

Read More